Construction Manager at Risk (CM@R)

CM@Risk utilizes a separate contract for a construction manager (CM). The CM begins work on the project during the design phase to provide constructability, pricing, and sequencing analysis of the design. The project sponsor generally holds a separate contract with the design team through these initial phases of the CM contract. The CM becomes the DB contractor when a guaranteed maximum price is agreed upon by the project sponsor and CM. The potential benefits of CM@RISK delivery include the continued advancement of the project during price negotiations and the potential for more optimal teaming because the CM can negotiate will all firms, rather than having to select from a limited number under DB delivery.