2. FURTHER INFORMATION
The Contractor shall submit any further or other information, data and documents that the Authority's Representative reasonably requires in order to determine whether he has a basis for raising comments or making objections to any Submitted Item in accordance with this Schedule. If the Contractor does not submit any such information, data and documents, the Authority's Representative shall be entitled to:
2.1. comment on the Submitted Item on the basis of the information, data and documents which have been provided; or
2.2. object to the Submitted Item on the grounds that insufficient information, data and documents have been provided to enable the Authority's Representative to determine whether he has a legitimate basis for commenting or objecting in accordance with this Schedule.