5. DOCUMENTATION MANAGEMENT
5.1. The Contractor shall issue [three (3)] copies of all Submitted Items to the Authority and compile and maintain a register of the date and contents of the submission of all Submitted Items.
5.2. The Contractor shall compile and maintain a register of the date of receipt and content of all Submitted Items that are returned or deemed to be returned by the Authority's Representative.