2. REQUIREMENT FOR AUTHORITY CONSENT
The Contractor shall obtain the Authority's prior written consent to any Qualifying Refinancing and both the Authority and the Contractor shall at all times act in good faith with respect to (a) any Refinancing or (b) any potential or proposed Refinancing under paragraph 9 of this Schedule 16.71
__________________________________________________________________________________________________
71 The Authority may terminate the Contract for a wilful breach of this paragraph 2 or of paragraph 9. In such circumstances, the amount of compensation payable to the Contractor shall be the same as that paid to the Contractor if the Contract is terminated under Clause 71 (Termination on Corrupt Gifts or Fraud). See Section 21.6 of SoPC4 (Termination for Breach of the Refinancing Provisions).