3.  EXCLUSIVITY OF REMEDY

Required drafting (see Section 22.7 of SoPC4) as follows:

Any payment of compensation shall be in full satisfaction of any claim which can be made against the Authority by the Contractor in relation to termination of this Contract or any Ancillary Document.  The compensation payable under Part 2 (Compensation following Authority Default or Authority Voluntary Termination or Authority Break Point Date Termination), Part 4 (Compensation following Corrupt Gifts and Fraud), Part 5 (Compensation on Termination for Force Majeure and Uninsurability) and Part 6 (Compensation Following Breach of the Refinancing Provisions) shall be the sole remedy of the Contractor against the Authority in respect of termination of the Contract.