PART 1  GENERAL PROVISIONS

Application of this Change Protocol

This Schedule 21 (Change Protocol) is divided into 61 Parts as follows:

Part 1:

applies to all Authority and Contractor Changes.

Parts 2- 4:

apply to Authority Changes from the Services Commencement Date and thereafter throughout the Services Period.

Part 5:

applies to Contractor Changes at any time during the Contract Period.

Part 6:

applies to Construction Changes (i.e. an Authority Change which affects the Works and which takes effect during the period from the date of this Contract until the [end of the defects liability period]153 under the Construction Sub-Contract and/or an Architectural Enhancement arising in accordance with paragraph 3.9 of Schedule 26 (Planning) in each case as shall be processed in accordance with Part 6 of this Schedule 21 (Change Protocol).

For the avoidance of doubt, Qualifying Changes in Law shall be treated as Authority Changes for the purposes of this Schedule 21 (Change Protocol) (but not for Schedule 19 (Revision of Base Case and custody)).




__________________________________________________________________________________________________

153  Amend to reflect the correct terminology for the Construction Sub-Contract (i.e. so that it applies to the final testing to be undertaken under the Construction Sub-Contract which is very often beyond the Acceptance Date in the Contract).