22.  ACCESS TO DOCUMENTS

The Contractor shall not allow the Construction Sub-Contractor or the Operating Sub-Contractor access to any document relevant to issues in dispute between the Authority and the Contractor save where:

22.1.  the document is relevant also to the issues relating to the Construction Sub-Contract Dispute or the Operating Sub-Contract Dispute as the case may be; and

22.2.  the Contractor has first delivered to the Authority a written undertaking from the Construction Sub-Contractor and/or the Operating Sub-Contractor (as appropriate) addressed to the Authority that they shall not use any such document otherwise than for the purpose of the dispute resolution proceedings under this Contract and that they shall not disclose such documents or any information contained therein to any third party other than the Adjudicator or the Arbitrator or any professional adviser engaged by the Construction Sub-Contractor or the Operating Sub-Contractor (as appropriate) to advise in connection with the dispute.