5.  OBLIGATIONS OF THE CONTRACTOR

5.1.  The Contractor shall:

5.1.1.  not cause or permit any Affiliate, associated or holding company of the Contractor or any entity or any third party over which it has control to object or procure any objection to any application for a Key Facility Environmental Permit; and

5.1.2.  not vary any application for a Key Facility Environmental Permit without the prior written consent of the Authority's Representative (which consent shall not be unreasonably withheld or delayed) and where the Contractor with such consent varies any application for a Key Facility Environmental Permit the Contractor shall inform the Authority's Representative of the variance to the application for a Key Facility Environmental Permit and (where appropriate and/or applicable) provide to the Authority's Representative any documents or letters relating to the variance.