9.2  Representatives of the Contractor

9.2.1  The Contractor's Representative shall be [                    ] or such other person appointed pursuant to this Clause.  The Contractor's Representative shall have full authority to act on behalf of the Contractor for all purposes of this Contract.  Except as previously notified in writing before such act by the Contractor to the Authority, the Authority and the Authority's Representative shall be entitled to treat any act of the Contractor's Representative in connection with this Contract as being expressly authorised by the Contractor and the Authority and the Authority's Representative shall not be required to determine whether any express authority has in fact been given.

9.2.2  The Contractor may by notice to the Authority change the Contractor's Representative.  Where the Contractor wishes to do so, it shall by written notice to the Authority propose a substitute for approval, taking account of the need for liaison and continuity in respect of the Project.  Such appointment shall be subject to the approval of the Authority (not to be unreasonably withheld or delayed).