16.6 Notification of Delays in Progress of the Works
Without prejudice to the provisions of Clause 16.5 above and the requirement of the Contractor to notify pursuant to Clause 20 (Delays), if either:
16.6.1 the Contractor becomes aware at any time that the actual progress of the Works may become or has been significantly delayed or has fallen behind the Construction Programme; or
16.6.2 it appears to the Authority's Representative at any time that the actual progress has been significantly delayed or has fallen behind the Construction Programme (and the Authority's Representative requests the Contractor's Representative to do so),
the Contractor's Representative shall submit to the Authority's Representative a report identifying the reasons for the delay and (where the Authority's Representative requires the Contractor's Representative to do so) the Contractor's Representative shall produce and submit to the Authority's Representative in accordance with Schedule 9 (Review Procedure) a revised Construction Programme showing the manner and the periods in which the Works will be carried out to achieve the Planned Services Commencement Date and/or showing the steps which are to be taken to eliminate or reduce the delay.