17.1 Responsibility for Design
Without prejudice to the generality of Clause 29 (Health and Safety) as between the Contractor and the Authority, the Contractor shall be entirely responsible for the safety of any design which forms part of the Works and/or the Services and for the adequacy, stability and safety of all site operations and methods of construction.