20.2  Supply of Information

Following service of a notice by the Contractor pursuant to Clause 20.1 (Notice) the Contractor shall promptly supply to the Authority any further information relating to the delay which:

20.2.1  is received by the Contractor; or

20.2.2  is reasonably requested by the Authority.