20.4  Time for Completion of the Works

If the carrying out of the Works or any part thereof is delayed and the delay is notified to the Authority in accordance with Clause 20.1 and such delay is attributable to:

20.4.1  a Compensation Event, then the provisions of Clause 39 (Compensation Events) shall apply; or

20.4.2  a Relief Event, then the provisions of Clause 40 (Relief Events) shall apply; or

20.4.3  a Force Majeure Event, then the provisions of Clause 69 (Termination on Force Majeure) shall apply.