21.3  Issue of Certificate

If a Notice of Non-Completion is served pursuant to Clause 21.2.8(b) the Contractor shall repeat the steps set out in Clauses 21.2.1 to 21.2.8 until all outstanding matters have been attended to and the relevant Test Certificate can be issued pursuant to Clause 21.2.8.