30. EQUIPMENT


Guidance drafting as follows:

30.1 The Contractor shall from the Services Commencement Date:

30.1.1 provide, repair, maintain and replace all Equipment necessary for the provision of the Services;

30.1.2 maintain all Equipment in accordance with Clause 26.1 (Maintenance);

30.1.3 use reasonable endeavours to ensure that all Equipment and related contracts, agreements, guarantees, warranties, bonds and insurances are assignable/novatable to the Authority or any third party who may provide the Services on expiry or termination;

30.1.4 at the end of each Contract Year prepare and provide to the Authority an updated Equipment List; and

30.1.5 six (6) Months prior to the Expiry Date, or, in the case of early termination of this Contract, twenty (20) Business Days following service of the relevant termination notice, prepare and provide to the Authority a final Equipment List ("Final Equipment List"). 65




______________________________________________________________________________________

65 Authorities to consider the use and practicality of this Clause on a project specific basis having regard to the nature of equipment used.