33.5 Step-In on Contractor Breach
If the Required Action is taken as a result of a breach of the obligations of the Contractor under this Contract, then for so long as and to the extent that the Required Action is taken, and this prevents the Contractor from providing any part of the Services:
33.5.1 the Contractor shall be relieved of its obligations to provide such part of the Services; and
33.5.2 in respect of the period in which the Authority is taking the Required Action, the Monthly Payment due from the Authority to the Contractor shall equal the amount the Contractor would receive if it were satisfying all its obligations and providing the Services affected by the Required Action in full over that period, less an amount equal to all the Authority's costs of operation in taking the Required Action.