33.7 Compensation for loss of Third Party Income
The Contractor shall be compensated for Third Party Income lost as a direct consequence of the Authority taking the Required Action on the following basis (less, in each case, the Authority's share of any Third Party Income):
33.7.1 in circumstances where the Contractor is not in breach, the Contractor's compensation for lost Third Party Income will be as set out in Schedule 19 (Revision of Base Case and Custody paragraph 6.5); and
33.7.2 in circumstances where the Contractor is in breach the Contractor compensation shall be limited to the difference (if any) between the amount of Third Party Income that the Authority receives during the period of the Authority taking Required Action less the Authority's costs of generating that income.