34.3  Adjustments to Unitary Charge

34.3.1  Where the tender price of a sub-contractor appointed by the Contractor pursuant to Clause 34 (Market Testing) (the "Successful Tenderer") is lower than the Latest Services Element, then the cost difference between the Successful Tenderer's tender price and the Latest Services Element shall be deducted from the Latest Services Element with effect from the relevant Market Testing Review Date and the Unitary Charge shall be adjusted to reflect that deduction in accordance with Clause 53 (Revision of Base Case and Custody).

34.3.2  Where the tender price of the Successful Tenderer is higher than the Latest Services Element, then the cost difference between the Successful Tenderer's tender price and the Latest Services Element shall be added to the Latest Services Element with effect from the relevant Market Testing Review Date and the Unitary Charge shall be adjusted to reflect that addition in accordance with Clause 53 (Revision of Base Case and Custody).