51.5 Third Party Waste Processing
51.5.1 The Contractor shall be entitled to accept, handle and process Third Party Waste at the Facility subject to the following provisions:
(a) that the Contractor accepts, handles and processes such Third Party Waste in accordance with all Legislation, Good Industry Practice and using all reasonable skill and care;
(b) that the acceptance, handling and processing of such Third Party Waste will not prevent the Contractor from Accepting, handling and/or processing Contract Waste [(up to the applicable Maximum Tonnage)] pursuant to and in accordance with the requirements of this Contract; and
(c) that any such Third Party Waste shall be of a [nature which is compatible with the Facility]103 and is such that it will not detrimentally affect the Contractor's ability to achieve Contract Targets and Performance Standards.
______________________________________________________________________________________
103 Authorities may wish to refer to other parameters, such as calorific value, where this is appropriate.