62.2  Common Law Rights of the Authority

Subject to:

62.2.1  any other express right of the Authority pursuant to this Contract; and

62.2.2  the Authority's right to claim, on or after termination of this Contract, the amount of its reasonable costs, losses, damages and expenses suffered or incurred by it as a result of rectifying or mitigating the effects of any breach of this Contract by the Contractor, save to the extent that the same has already been recovered by the Authority pursuant to this Contract or has been taken into account to calculate any compensation payable by the Authority pursuant to Clauses 66 (Compensation on Termination for Authority Default), 68 (Compensation on Termination for Contractor Default), 70 (Compensation on Termination for Force Majeure), 72 (Compensation on Corrupt Gifts and Fraud) 74  (Compensation on Voluntary Termination by the Authority)[, 74B (Compensation on Termination on an Authority Break Point Date)] or 76 (Compensation on Termination for Breach of the Refinancing Provisions),

the sole remedy of the Authority in respect of a failure to provide the Services in accordance with this Contract shall be the operation of Schedule 4 (Payment Mechanism).