62.6 No Double Recovery
Notwithstanding any other provision of this Contract, neither Party shall be entitled to recover compensation under this Contract or any Ancillary Document or any other agreement in relation to the Project in respect of any loss that it has incurred (or any failure of the other Party) to the extent that it has already been compensated in respect of that loss or failure pursuant to this Contract, any Ancillary Document or otherwise.