69.1  Obligations

No Party shall be entitled to bring a claim for a breach of obligations under this Contract by the other Party or incur any liability to the other Party for any losses or damages incurred by that other Party to the extent that a Force Majeure Event occurs and it is prevented from carrying out obligations by that Force Majeure Event.  For the avoidance of doubt, the Authority shall not be entitled to terminate this Contract for a Contactor Default if such Contractor Default arises from a Force Majeure Event (but without prejudice to Clauses 69.5 (Unable to Agree) or 69.7 (Notice to Continue).