69.6 Consequences of Termination
If this Contract is terminated under Clause 69.5 (Unable to Agree) or Clause 69.7 (Notice to Continue):
69.6.1 compensation shall be payable by the Authority in accordance with Clause 70 (Compensation on Termination for Force Majeure); and
69.6.2 the Authority may, subject to Clauses 80.4.2 and 80.4.3 require the Contractor to transfer its title, interest and rights in and to any Assets [(or such part of the Assets as may be required by the Authority)] to the Authority.