83.2  Duty to Comply with Legislation

Without prejudice to the generality of Clause 44 (Change in Law) and Clause 83.1 (Legislation), the Contractor shall:

83.2.1  give all notices;

83.2.2  obtain and maintain in full force and effect; and

83.2.3  pay all fees required to be paid or given,

by any Legislation and/or Guidance and/or in relation to all Consents relevant to the provision of the Works and Service and as required for the proper performance of the Contractor's duties and obligations under this Contract and under any Ancillary Document.