87.3  Assignment to the Authority

The Contractor hereby assigns to the Authority with full title guarantee (free from all liens, charges, encumbrances and third party rights), as a present assignment of present and future rights, all right title and interest in and to:

87.3.1  the Project Data, all copies thereof and all Intellectual Property Rights in any Project Data in each case generated by or for the Contractor and/or any Contractor Related Party pursuant to this Contract;

87.3.2  any Intellectual Property Rights and goodwill generated by the Contractor and/or any Contractor Related Party through the use of the Trade Marks,

with the intent that they shall vest in the Authority forthwith upon the same coming into existence.174




______________________________________________________________________________________

174  Consider appropriateness of Clauses 87.2, 87.3 and 87.6 on a project specific basis.