90.3 Examination by the Authority or its Representatives
Without limitation to Clause 90.2 (Contractor Obligations), no examination or lack of examination by the Authority or any person authorised on its behalf, of the Contractor's drawings, documents, calculations or details relating to the design, construction, completion, commissioning and testing of the Facility or the management or provision of the Service or otherwise nor any comment, rejection or approval expressed by such person in regard thereto, either with or without modifications, shall in any respect relieve or absolve the Contractor from any obligations or liability under or in connection with this Contract and any Ancillary Document.