2.2.8 Termination As A Result of Planning Delay

As noted above the Authority is not obliged to pursue a Revised Project Plan. It has the option to terminate before such a Plan is developed or having seen the Contractor's plan and rejected it. The termination option will normally give rise to an obligation for the Authority to pay compensation to the Contractor. This issue is explored in depth in Section 8

PFI Projects

The Authorities should notify Defra as soon as it reasonably expects the Contract to terminate for a failure to obtain planning consent.  The Authority's ongoing entitlement to WI Credits will be reviewed in the light of the specific circumstances.