Appendix E - Key Dates and Time Limits

 
 


The table below defines those key dates relating to the project that are either important in terms of the overall delivery programme or that have a contractual consequence if there is a delay.  It is the same as that found at Schedule 8 of the WIDP Contract, except an additional column is added to insert any comments from the Contract Management Team.

Milestone

Date

[unless expressed otherwise, can be either a fixed date or on a time elapsed basis]

Contractual consequence

 

Comments from the Contract Management Team

[e.g. who is responsible for monitoring this date]

Financial Close

 

 

 

[Interim Services Commencement Date]

 

 

 

Planning - preparation and pre application discussions

 

 

 

Environmental Permit - preparation and pre application discussions

 

 

 

Planning - submission of Planning Application

 

 

 

Planning Application Longstop Date

 

Failure to submit Planning Application by Planning Application Longstop Date is a Contractor Default

 

Environmental Permit - submission of Environmental Permit Application

 

 

 

Judicial review or challenge period assumed

 

 

 

Planning Permission Longstop Date

 

Where the Contractor fails to achieve Planning Permission or to secure an Environmental Permit by the Planning Permission Longstop Date:

(a) in the case of planning failure, the Authority is obliged to terminate the Contract pursuant to paragraph 3.5 of Schedule 26 (Planning) or to require the Contractor to submit a Revised Project Plan;

(b) in the case of failure to secure an Environmental Permit, the Authority is obliged to terminate the Contract pursuant to paragraph 11.1.5 of Schedule 27 (Approach to Permit Risk)

 

Planned Works Commencement Date

 

Failure to commence the Works by [      ] Months after the Planned Works Commencement Date is a Contractor Default

 

Works Period

 

 

 

Commissioning Period

 

 

 

Planned Readiness Date

 

 

 

Planned Acceptance Date

 

 

 

Planned Services Commencement Date

 

 

 

Readiness Longstop Date

[  ] Months after the Planned Readiness Date

[Failure to obtain Readiness Certificate by Readiness Longstop Date is a Contractor Default]

 

Acceptance Longstop Date

[12] Months after the Planned Services Commencement Date

Failure to obtain Acceptance Test Certificate by Acceptance Longstop Date is a Contractor Default

 

Expiry Date

The [        ] anniversary of the date of this Contract