The table below defines those key dates relating to the project that are either important in terms of the overall delivery programme or that have a contractual consequence if there is a delay. It is the same as that found at Schedule 8 of the WIDP Contract, except an additional column is added to insert any comments from the Contract Management Team.
Milestone | Date [unless expressed otherwise, can be either a fixed date or on a time elapsed basis] | Contractual consequence
| Comments from the Contract Management Team [e.g. who is responsible for monitoring this date] |
|
|
| |
[Interim Services Commencement Date] |
|
|
|
Planning - preparation and pre application discussions |
|
|
|
Environmental Permit - preparation and pre application discussions |
|
|
|
Planning - submission of Planning Application |
|
|
|
Planning Application Longstop Date |
| Failure to submit Planning Application by Planning Application Longstop Date is a Contractor Default |
|
Environmental Permit - submission of Environmental Permit Application |
|
|
|
Judicial review or challenge period assumed |
|
|
|
| Where the Contractor fails to achieve Planning Permission or to secure an Environmental Permit by the Planning Permission Longstop Date: (a) in the case of planning failure, the Authority is obliged to terminate the Contract pursuant to paragraph 3.5 of Schedule 26 (Planning) or to require the Contractor to submit a Revised Project Plan; (b) in the case of failure to secure an Environmental Permit, the Authority is obliged to terminate the Contract pursuant to paragraph 11.1.5 of Schedule 27 (Approach to Permit Risk) |
| |
| Failure to commence the Works by [ ] Months after the Planned Works Commencement Date is a Contractor Default |
| |
|
|
| |
|
|
| |
|
|
| |
Planned Acceptance Date |
|
|
|
|
|
| |
[ ] Months after the Planned Readiness Date | [Failure to obtain Readiness Certificate by Readiness Longstop Date is a Contractor Default] |
| |
[12] Months after the Planned Services Commencement Date | Failure to obtain Acceptance Test Certificate by Acceptance Longstop Date is a Contractor Default |
| |
The [ ] anniversary of the date of this Contract |
|
|