Managing risks: summary

2.53 The Department has generally managed risks well in the PFI projects we examined. Our analysis above shows that risk has also been managed well in six out of the eight case study projects evaluated and that out of ten risk categories nine show either a low or some potential risks to value for money (moderate risk). Figure 18 below summarises our assessment:

 

18

Assessment of Risk Performance for the Eight case Studies

 

 

Risk 1

Specification of the asset or service

Risk 2

Delivery of a PFI solution

Risk 3

Delivery of the ongoing service

Risk 4

Service user and stakeholder satisfaction with delivery

Risk 5

Technology and latent defects

Risk 6

Environment and safety

Risk 7

Performance monitoring and management regimes

Risk 8

Relationships with contractors

Risk 9

Resources and skills

Risk 10 Risk management processes

 

 

 

Procurement phase

Management of the contracts

Procurement phase

Construction or service implementation phase

 

 

 

 

 

 

 

 

 

 

Overall assessment of current risk to the Department:

Significant risks to value for money

Some risks to value for money

Some risks to value for money

Low level of current risk to value for money

Low level of current risk to value for money

Low level of current risk to value for money

Some risks to value for money

Low level of current risk to value for money

Some risks to value for money

Low level of current risk to value for money

Some risks to value for money

Some risks to value for money

 

 

Heavy Equipment Transporter

 

 

Field Electrical Power Supplies

 

 

Medium Support Helicopter Aircrew Training Facility

 

 

Armoured Vehicle Training Service

N/A

N/A

N/A

N/A

N/A

N/A

N/A

 

 

Main Building Refurbishment

 

 

Defence Animal Centre

 

 

Defence Fixed Telecommunications System

 

 

Tidworth Water and Sewerage

 

Source: NAO review of case studies