APPENDIX ONE The case studies

This part provides more information about each of the eight case study projects that we examined and explains how they were selected.

1  As part of our review of PFI in the Ministry of Defence, we examined a selection of eight case study projects, which illustrate the diverse nature of the Department's portfolio and provide an insight into the types of challenges presented by their PFI projects. We chose two projects from each category of service: equipment, training, accommodation and other support projects.

2  As shown in Figure 20, we also selected the eight projects to give variety according to maturity (how long the project has been operational), the type of service provided, the proximity of the service to the front line of operations and also the size of deal (based on the capital value of the project).

3  The eight case study projects also spent varying amounts of time in procurement. All the operational contracts will run until at least 2012 and, in the case of the Medium Support Helicopter Aircrew Training facility may run until 2037.

 

19

The eight case study projects

 

Type of service

Project

 

Equipment

Heavy Equipment Transporter

 

 

Field Electrical Power Supplies

 

Training

Medium Support Helicopter Aircrew Training Facility

 

 

Armoured Vehicle Training Service

 

Accommodation

Ministry of Defence Main Building Refurbishment

 

 

Defence Animal Centre

 

Other Support

Defence Fixed Telecommunications System

 

 

Tidworth Water and Sewerage

Source: National Audit Office analysis of case study projects

 

20

The eight case study projects illustrate the diverse nature of the Department's PFI project portfolio, based on size, project maturity and the proximity of the service to the front line

 

Project

Type

Maturity

Support vs. Front Line

Size of capital value

 

Heavy Equipment Transporter

Equipment

Early Operation

close to the front line

Medium

 

Field Electrical Power Supplies Service

Equipment

Early Operation

close to the front line

Medium

 

Medium Support Helicopters Aircrew Training Facility

Training

Mature operation

Support - but influential on the front line

Medium

 

Armoured Vehicles Training Service

Training

Recently cancelled PFI procurement

Support - but influential on the front line

Medium

 

Defence Animal Centre

Accommodation

Mature operation

Support

Small

 

Main Building Redevelopment

Accommodation

Mature operation

Support

Large

 

Tidworth Water and Sewerage

Other support

Mature operation

Support

Small

 

Defence Fixed Telecommunications Systems

Other support

Mature operation

Support

Large

Source: National Audit Office analysis of case study projects

 

21

Time line showing the indicative procurement and operational phases of the eight case studies

Source: National Audit Office analysis of case studies.

NOTES

1  Option to extend to 2037.

2  Option to extend to 2023.