Part 2 A national standard IT system has been under development for over ten years
>
The deal was renegotiated after contract signature leading to a new contract in May 2000
The deal was renegotiated after contract signature leading to a new contract in May 2000
More Information
ICL threatened to walk away from the deal
The Department decided to continue with the contract
A revised contract for £319 million was signed in May 2000