Part 2 A national standard IT system has been under development for over ten years
>
ICL and the Department entered into further renegotiations of the contract in October 2001 but could not reach agreement
>
ICL had performed poorly on the contract and tried to recover the situation.
ICL had performed poorly on the contract and tried to recover the situation.
2.42
The Department
had lost confidence in ICL's capacity to deliver the full Libra project.
More Information
ICL realised it could not develop MASS in the way it initially thought it could
There was little continuity in ICL's management
ICL started writing computer programmes too early
ICL did not meet the target dates for delivery of the core application
ICL tried to recover the situation