By 30 September 2002 ICL had received payments totalling £63.1 million

2.69  The Department has paid ICL £50.8 million so far (£3.9 million for paper deliverables, £36.4 million for acceptance of the infrastructure by Magistrates' Courts Committees and £10.5 million for the Memorandum of Understanding negotiations). Magistrates' Courts Committees have paid ICL £12.3 million in weighted caseload payments. ICL has incurred performance deductions of £59,500.

2.70  If the project now proceeds according to plan, ICL is likely to receive a further £175.9 million, making £239 million in total. This comprises £232 million under the revised infrastructure contract and £7 million for work on the cancelled core application.