3.47 Given the extent to which difficulties were not resolved during the procurement period, the risks to the project when the contract was awarded to Pathway were likely to have a major effect on the cost and timescale of the project, however strong were the arrangements for managing implementation. The purchasers attempted to manage the major risks that re-emerged during the system development and implementation stage mainly through:
■ formal risk management procedures operated by a joint delivery authority, replaced in April 1998 by a Post Office Counters Ltd team;
■ agreeing a project replan with Pathway in February 1997;
■ commissioning an independent review of the entire programme from PA Consulting when slippage continued, and acting on the recommendations; and
■ the risk management arrangements of Post Office Counters Ltd from April 1998, when their Horizon team took over responsibility for the contract with Pathway.