Staff Costs, including accommodation, clerical support, expenses and printing. Tuberail
External Costs
Includes Asset Management, Financial, Legal, Technical, Public Relations, Human Resources, Risk Assessment and other Due Diligence.
Lead firms include Linklaters, Allen & Overy, Arthur Anderson, S&P and Moody's.
Amount Paid
Following a claim by Tuberail in September 2002, the London Transport Board agreed to full payment of the £11 million requested. This was based on accepting that Tuberail had diligently followed London Underground's instructions during a prolonged bidding process.