2.2 The amount of PFI credits allocated to the Department as part of the Government spending reviews has been a factor affecting the number and size of PFI projects local authorities have undertaken. PFI credits were limited in the early years of the programme (especially prior to 2003) (Figure 7). There were not always sufficient PFI credits available to fund all local authorities' requests for financial support and it was necessary to ration funds between projects.