The table shows that the technical transition assessment proceeded separately from the main procurement, and that GCHQ did not realise the likely scale of the costs until its review team reported in November 1999.
Year | Month | Procurement event | Technical transition estimate at time of event |
1997 | April | Business case for PFI project approved by Directorate | £41 million |
| May | Foreign Secretary approval to proceed with PFI approach |
|
| August | Long list of bidders announced |
|
| September | Short list of four bidders announced and Invitations to Negotiate issued |
|
| November | Invitations to tender issued to bidders |
|
| December | Revised Business Case and Project Plan approved by Board |
|
1999 | February | Deadline for tender responses |
|
| June | Announcement of two short-listed bidders |
|
| September | Directorate approval of IAS (GSL) as preferred bidder | £60 million |
| December | Business case to Treasury |
|
1999 | January | Project Manager resigned and new Project Director appointed |
|
| February | Objective set to produce detailed technical transition plan |
|
| October | Launch of technical transition review team to assess technical transition issues and costs |
|
| November | Review team report that technical transition costs will be around ten times higher than previously estimated | £50 million |
| December | Review team asked to consider ways of reducing technical transition costs | £308 million1 |
2000 | February | Treasury cap technical transition spending at £308 million |
|
| March | Project re-designated as New Accommodation Programme to include whole business move |
|
| April/May | Lieutenant General Sir Edmund Burton produced his report on management of the project |
|
| June | £408.65 million bond issued |
|
|
| Contract signed with IAS |
|
2001 | January/October | Continuing re-assessment of technical transition costs | £308 million1 |
2002 | June | Estimated total cost for moving GCHQ's business into the new building and for providing accommodation and services for the 30 years of the PFI deal: £1,623 million in cash terms, £783 million Net Present Value, including extending technical transition costs up to 2012 |
|
NOTE
1. This technical transition estimate covers the five year period to 2004-05 and represents the approved budget.