Question 92 (Mr Sadiq Khan): Could we also have a breakdown of the £14.9 million, the wasted costs.

Request from SHA for PHC costs (excluding carrying costs of £490k).

Expenditure by year for Paddington Health Campus Project & Forecast to 30 June 2005




PHC Spend by Year from 1999



WLPF

1999-2000
£000's



PHC

2000-01
£000's



PHC

2001-02
£000's



PHC

2002-03
£000
's



PHC

2003-04
£000's



PHC

2004-05
£000's


PHC from

01-04-05 to
30-06-05
£000's

PHC &
WLPF Total

cost to

30-06-05

£000
's

Advisers

1,479

231

520

947

2,991

1,536

88

7,792

Pay

155

209

360

843

1,531

1,389

275

4,762

Accommodation & other Project costs 18

 

62

46

309

416

337

84

1,272

Total

1,652

502

926

2,099

4,938

3,262

447

13,827

NOTES:

1. Direct Costs from Partnerships UK (PUK)

282

380

409

0

1,071

(not charged to budgets-but payable by Trusts on termination of Project)

2.  Carrying costs are chargeable on PUK direct and indirect costs-total £390k

0

3.  WLPF-West London Partnership Forum (hosted by former Kensington, Chelsea and Westminster Health Authority) to October 2000

4.  PHC - Paddington Health Campus (St Mary's NHS Trust as paymaster) from November 2000

5.  Delayed settlement costs of £100k (50-50 Trust split)

0

 

 

 

 

 

14,898

 

PHC Funding by Year from 1999

WLPF 
1999-2000
£000's

PHC
2000-01
£000's

PHC
2001-2
£000's

PHC
2002-3
£000's

PHC
2003-4£000's

PHC 2004-5
£000's

PHC from
01-04-05 to
30-06-05
£000's

PHC &
WLPF Total
funding to
30-06-05
£000's

Funding-cash mgt for project (suplus)/deficit b/f

0

-246

256

82

-172

671

545

0

WLPF funding for outline planning application

-572

0

0

0

0

0

0

-572

SMH (60%) re 03-04 deficit & wind up

-326

0

0

326

0

-313

-45

-358

BH (40%) re deficit and wind up

 

 

 

 

 

-208

-30

-238

SMH-PUK unpaid 50%

 

 

 

 

 

 

-273

-273

RBH-PUK unpaid 50%

 

 

 

 

 

 

-273

-273

SMH share of IC wind up contribution

 

 

 

 

 

 

125

125

RBH share of IC wind up contribution

 

 

 

 

 

 

125

125

NWL SHA support for 03-04 deficit

0

0

0

0

0

-150

0

-150

Less Imperial College Contribution (5.08% of 50%)

0

0

0

0

-125

-58

0

-183

IC share of PUK-wind up costs

0

0

0

0

0

0

-250

-250

Less PUK Funding (payable on termination of Project)

0

0

0

-680

-2,469

-1,246

0

-4,395

PCT funding (NLLondon Secor PCTs-1% of SLA)-SMH

0

0

0

0

0

-1,257

-331

-1,588

PCT funding (NLLondon Secor PCTs-1% of SLA)-RBH

 

 

 

 

 

-156

-41

-197

Less RHA/SHA Funding (from 1.75% of OBC CAPEX)

-1,000

0

-1,100

-2,000

-1,500

0

0

-5,600

Total funding

-1,898

-246

-844

-2,272

-4,266

-2,717

-447

-13,827

(suplus)/deficit c-f

-246

256

82

-172

671

545

0

0

 

 

£000's

 

Total costs-funding including PUK direct, carrying costs and delayed

 

14,898

settlement

 

 

Imperial conts @50% of 5.08%

 

-183

Imperial PUK share & winding up

 

-250

SMH-PUK share-excluding carrying costs

approx 50%

-2,748

Less SMH share of IC cont to winding up

50%

125

Less SMH share of SHA support for PUK settlement

50%

1,000

SMH/PUK unpaid

50%

-273

SMH deficit-wind up

60%

-358

RBH/PUK share-excluding carrying costs

approx 50%

-2,718

Less RBH share of IC cont to winding up

50%

125

Less RBH share of SHA support for PUK settlement

50%

1,000

RBH/PUK unpaid

50%

-273

RBH deficit-wind up

40%

-238

WLPF-contribution from W.London HA's

 

-572

Sector PCT's-SMH SLAs

 

-1,588

Sector PCTs-RBH SLAs

 

-197

RHA-SHA

 

-5,750

SHA assistance with PUK settlement (£1m assistance for each of SMH and RBH)

-2,000

Surplus/deficit

 

0

Summary-Shares of PHC Costs

£000's

 

Imperial

2.9%

-433

SMH

15.1%

-2,254

RBH

14.1%

-2,104

Sector PCT's inc WLPF

15.8%

-2,357

RHA-SHA

52.0%

-7,750 

 

 

-14,898

Note NAO report quotes £15 million (£14.9 million) which excludes PUK carrying costs and deferred settlement costs (£0.5 million)