34 In April 2005, the Senior Responsible Officer advised the Accounting Officer that the project was no longer economically viable. Capital costs had risen following the lengthy legal delays; and anticipated benefits had reduced due to a 'marked' improvement in the handling of asylum claims for dispersed asylum applicants.