2.1 The results of our census demonstrate that the majority of English PFI central government projects involving construction have been delivered on time and at the agreed price to the public sector. This is better than has been achieved in the past by traditionally procured projects. Most public sector project managers were satisfied with the resulting design and build quality. However, it is not possible to judge whether these projects could have achieved these results using a different procurement route.