Part 2 Our census of projects generally supported the hypothesis
>
Most PFI building projects were delivered by the time specified in the contract - a further improvement compared with previous procurement experience
Most PFI building projects were delivered by the time specified in the contract - a further improvement compared with previous procurement experience
More Information
Seventy six per cent of the projects surveyed were completed and available for use by the time specified in the contract
The census results are a considerable improvement over historical experience in traditional building procurement
Only three of the PFI building projects surveyed had not been completed within two months of the date specified in the contract