The Department's costs were £44 million, much higher than expected

1.22  The costs to the Department of the PPP process comprised two main elements:

  their direct advisory costs; and

  costs recharged to them by NATS and the Civil Aviation Authority.

Lacking other information the Department based their budgets on indicative estimates prepared by shortlisted firms, which varied widely.