Delivery times

2.10  The time taken to develop business cases has increased over time (Figure 6 overleaf). The Department took one month to assess bids for funding from local authorities for round two. This time has increased steadily in subsequent rounds, most recently taking nine months. Increases partly reflect more rigorous scrutiny of bids by the Department. Once projects have been accepted onto the programme they develop business cases, and in early rounds most local authorities took a year or less to do so while many later projects have taken closer to two years. The increases are a result of the Department's agreement with the Treasury to ensure business cases are robust before they proceed for formal approval. The Department expects round six projects to take between 12 and 18 months to develop their business cases.

2.11  Across the programme the Department and local authorities' estimates for the time it would take to procure projects have been overly optimistic (Figure 7 on pages 24 and 25). All signed projects have been delivered later than the targets set out in their business cases. The delays range between five months, and five years and one month, the average being two years and six months. All but four projects currently in procurement have already exceeded their targets, demonstrating that the Department and local authorities were over-optimistic about how long procurement would take.

2.12  For round six projects the Department has set procurement targets of 30-36 months for council housing projects and 25-29 months for non-council social housing projects. One early council housing project and four round three non-council social housing projects were procured within these targets which shows quicker procurement is achievable. Other projects took considerably longer with council housing projects taking between 34 and 75 months and non-council social housing projects between 26 and 43 months.9 In our 2007 report Improving the PFI Tendering Process we found that procurement periods in PFI procurement overall lasted an average of 34 months.10

2.13 The Department learnt lessons from early projects and developed guidance to improve procurement times but it is difficult to assess whether times are improving as many projects are not sufficiently advanced for us to make an assessment. Some have already exceeded the Department's new targets. An additional complication is that more recent projects are procured under new European Union rules which are perceived to lengthen procurement times.

2.14 The Department has monitored the progress of construction and refurbishment work after contracts have been signed through regular meetings but there have been gaps in the process and a more formal system is now in place to do this. With a few exceptions projects told us that milestones are largely being met and where there are delays these have had minimal impact on the overall project.

Figure 6
Time taken to assess bids and develop business cases

Council housing

Projects

Non-council social housing

Projects

NOTES

1  Little London was delayed and is now being jointly procured with a round five project, Beeston Hill & Holbeck.

2  These projects have not yet had business cases approved, so the time shown is that which has elapsed to date.

3  The Extra Care Housing business case has only received conditional approval to date.

4  Two non-council social housing projects have been excluded due to lack of data.

Source: National Audit Office analysis of data from the Department for Communities and Local Government and local authorities

 

Figure 7
Comparison of procurement times to targets

Signed projects have experienced significant delays

Council housing

Non-council social housing

Project

Target date for contract signature

Actual date of contract signature

Delay (months)

 

Project

Target date for contract signature

Actual date of contract signature

Delay (months)

Plymouth Grove (Manchester)

February 2001

March 2003

25

 

Holmewood PFI Housing Scheme (North East Derbyshire)

March 1998

August 1998

5

Canning Town (Newham)

July 2001

June 2005

47

 

Non-HRA PFI Scheme (Selby)

January 2002

March 2004

26

Hawthorn Fields (Sandwell)

October 2001

March 2006

53

 

Nursing Homes and Extra Care (Hammersmith and Fulham)

April 2002

March 2004

23

Swarcliffe (Leeds)

October 2001

March 2005

41

 

Anson & Blenheim Close / John Morris House (Warrington)

January 2004 

September 2004

8

North Whitley (Reading)

November 2001

March 2004

28

 

New Homes For Old (Coventry)

March 2004

March 2006

24

Chalcots Estate (Camden)

January 2002

May 2006

52

 

New For Old (Croydon)

March 2006

December 2006

9

Street Properties 1 (Islington)

March 2002

March 2003

12

 

Housing and Adult Social Care (Brent)2

December 2004

December 2008

48

Miles Platting (Manchester)

May 2003

March 2007

48

 

Extra Care Housing 1 (Cheshire)

November 2006

October 2007

11

Brockley Housing (Lewisham)

October 2003

June 2007

44

 

Better Homes Active Lives (Kent)

January 2007

October 2007

9

Sheltered Housing (Oldham)

October 2003

October 2006

36

 

Independent Living (Leeds)

October 2007

June 2008

8

Street Properties 2 (Islington)

December 2003

September 2006

33

 

Inner City Regeneration (Derby)

not known

not known

not known

Forest Gate (Newham)

December 2003

January 2009

61

 

 

 

 

 

Stanhope Estate (Ashford)1

April 2004

April 2007

36

 

 

 

 

 

 

Most projects still in procurement are already later than their target date

Council housing

Non-council social housing

Project

Target date for contract signature

Delay to date (months)

 

Project

Target date for contract signature

Delay to date (months)

Excellent Homes for Life (Kirklees)

March 2007

39

 

Wiltshire Non-HRA PFI Scheme (West Wiltshire)4

March 2008

32

Myatts Field (Lambeth)

April 2008

26

 

PFI Housing (Derby)

March 2008

27

Gateways to Oldham (Oldham)

April 2009

14

 

Priority Homes (Woking)

October 2010

-

Beeston Hill & Holbeck (Leeds)

January 2010

5

 

Excellent Homes for All (Kent)

September 2011

-

Brunswick (Manchester)

March 2010

3

 

 

 

 

Quality Homes for Older People (North Tyneside)

July 2010

-

 

 

 

 

Creating a New Pendleton (Salford)

March 2011

-

 

 

 

 

Little London (Leeds)3

not known

not known

 

 

 

 

 

 

 

 

 

 

 

Notes

1  After losing confidence in the initial procurement Ashford ended the process and retendered the contract extending the overall procurement time.

2  After the project was endorsed Brent decided to put the project on hold delaying the start of procurement.

3  Little London is now being jointly procured with a round five project, Beeston Hill & Holbeck.

4  The Wiltshire scheme has gone to a single bidder which means additional time is being spent benchmarking costs.

Source: National Audit Office analysis of data from the Department for Communities and Local Government and local authorities




______________________________________________________________________________________

9  One very early project took 10 months to procure. At £360,000 in value this project is considerably smaller than all other projects in the programme and so not representative.
10  This was the average for all central Government PFI contracts including schools and hospitals that reached financial close between April 2004 and June 2006. See National Audit Office report, HC 149 
2006-07, 8 March 2007.