Part 3 Why the Inland Revenue decided to extend the NIRS 2 contract and the steps they have taken to minimise the risk of further difficulties
3.1 This part examines the options available to the Inland Revenue for carrying out the additional work, how the Department evaluated them, and how they have used the extension to change the way the contract is managed.