Part 1: The scope of the project may not have maximised value for money
>
The Department did not fully review the implications of pursuing a privately financed deal
The Department did not fully review the implications of pursuing a privately financed deal
More Information
The Department originally sought a publicly funded procurement, but also invited innovative solutions
A privately financed project developed during the competition
The Department did not make clear that highly specified services were to be included
Risk allocation in the contract is more like a traditional outsourcing than a Private Finance Initiative contract