Part 2 The 1998 PFI contract for the College's permanent home was good value for money and provides useful lessons
>
The change to the use of the PFI led to a delay
The change to the use of the PFI led to a delay
More Information
The Department changed the target date to September 1999
Contract negotiations delayed the delivery of the new facilities by a year
Despite the delay it is still likely that the use of the PFI offered best value for money