Question 32-34 (Dr Pugh): The age of the primary school estate compared to secondary school estate
Most primary schools buildings were built more than 25 years ago and most of these are now approaching the end of their original design lives.
The table below shows percentages of schools buildings in age bands based on 2006 analysis.
|
|
Primary |
Secondary |
|
Pre 1919 |
18% |
8% |
|
Inter-war |
11% |
9% |
|
1945-66 |
23% |
29% |
|
1967-76 |
24% |
22% |
|
Post 1976 |
20% |
27% |
|
Temporary |
4% |
5% |
Question 34 (Dr Pugh): Summary of work undertaken to each completed school, and the age of each rebuilt, remodelled or refurbished school completed
When local authorities consider options for the level of new build, remodelling or refurbishment required at the schools in their BSF project they do not, specifically, consider the age of each school but rather the condition and suitability of the buildings and they also take into account pupil place planning decisions. The general BSF policy position is that schools which are less than ten years old do not attract funding, although they may receive ICT funding for a local authority managed service.
Condition need-which focuses on investment need in the premises to maintain them in good condition and to ensure safe and continuous operation, and other requirements that may involve building regulations or other non educational statutory provisions. It also takes into account aspects of health and safety, for example in relation to the types of materials used in the construction, such as asbestos.
Suitability need-which focuses on the ability of the premises to meet curriculum or management needs and other issues impacting on the role of the local authority in raising educational standards. This measurement considers premises shortcomings that impact users, including teaching and non-teaching spaces, environments and equipment. Suitability also takes into account aspects of health and safety, for example in relation to the adequacy of fire escape routes, ventilation and lighting.
Pupil place planning-which local authorities undertake by forecasting the demand for school places over a ten year period by looking at live birth data and making assumptions about school choice trends from post-code areas into primary schools and primary schools in secondary. This is then finessed to take account of changes in cross-border movement and new housing.
The table below provides details of the 54 school projects which have been completed to date-including the 12 schools which have opened since the NAO report was finalised. This does not include the age of the "predecessor" school as this information is not held centrally by PfS.
|
Local authority |
School |
Date of opening |
Summary of work carried out |
|
|
Complete New Build |
|
|
|
|
|
Solihull |
Forest Oak and Merstone Schools |
May 06 |
New Build centre for inclusive learning delivered as a BSF "quick win" project |
D&B |
|
STaG |
Bamburgh School (Horsley Hill Community Campus) |
Oct 06 |
New build school delivered as a BSF "quick win" project |
D&B |
|
Bristol |
Bristol Brunel Academy |
Sep 07 |
New build school delivered by the LEP |
|
|
Haringey |
Haringey Sixth Form Centre |
Sep 07 |
New build sixth form centre delivered as a BSF "quick win" project |
D&B |
|
Stoke |
Birches Head |
Nov 07 |
New build school delivered as a BSF "quick win" project |
D&B |
|
Lambeth |
The Michael Tippett School |
Feb 08 |
New build special school delivered as a BSF "quick win" project |
D&B |
|
Stoke |
Sandon High School |
Feb 08 |
New build school delivered as a BSF "quick win" project |
D&B |
|
Kent |
Ifield School |
Mar 08 |
New build sixth form centre delivered as a BSF "quick win" project |
D&B |
|
Bristol |
Bristol Metropolitan College |
Apr 08 |
New build school delivered by the LEP |
|
|
Leeds |
Cockburn College of Arts |
Sep 08 |
New build school delivered by the LEP |
D&B |
|
Bradford |
Titus Salt School |
Sep 08 |
New build school delivered by the LEP |
|
|
Bradford |
Tong High School |
Sep 08 |
New build school delivered by the LEP |
|
|
Bradford |
Buttershaw Business and Enterprise College |
Sep 08 |
New build school delivered by the LEP |
|
|
Bristol |
Brislington Enterprise College |
Sep 08 |
New build school delivered by the LEP |
|
|
Lancashire |
Burnley Campus (Thomas Whitham Sixth Form) |
Sep 08 |
New build school delivered by the LEP |
|
|
Lancashire |
Pendle Vale College (Pendle Vale Campus) |
Sep 08 |
New build school delivered by the LEP |
|
|
Lancashire |
Pendle Community High School (Pendle Vale Campus) |
Sep 08 |
New build school delivered by the LEP |
|
|
Lancashire |
Shuttleworth College |
Sep 08 |
New build school delivered by the LEP |
|
|
Leeds |
Allterton High School |
Sep 08 |
New build school delivered by the LEP |
|
|
Leeds |
Pudsey Grangefield School |
Sep 08 |
New build school delivered by the LEP |
|
|
Leeds |
Rodillian School |
Sep 08 |
New build school delivered by the LEP |
|
|
Leeds |
Temple Moor High School |
Sep 08 |
New build school delivered by the LEP |
D&B |
|
Manchester |
Gorton Education village (Melland High School) |
Sep 08 |
New build school delivered by the local authority framework |
D&B |
|
Newcastle |
Walbottle Campus Technology College |
Sep 08 |
New build school delivered by the LEP |
|
|
Newcastle |
Walkergate Primary School |
Sep 08 |
||
|
Newcastle |
Stocksfield Avenue Primary School |
Sep 08 |
||
|
Solihull |
Lanchester School |
Sep 08 |
||
|
Waltham Forest |
Frederick Bremer |
Sep 08 |
New build school delivered by the LEP |
|
|
Solihull |
Park Hall School |
Oct 08 |
New build school delivered by the local authority framework |
|
|
Lambeth |
Park Campus |
Nov 08 |
New build Pupil Referral Unit |
D&B |
|
Newcastle |
Kenton School |
Nov 08 |
||
|
Bristol |
The Bridge Learning Campus |
Jan 09 |
New build school delivered by the LEP |
|
|
Sheffield |
Talbot Special School |
Jan 09 |
New build special school delivered by the LEP |
|
|
Sheffield |
Newfield Secondary School |
Jan 09 |
New build school delivered by the LEP |
|
|
Sheffield |
Silverdale Secondary School |
Jan 09 |
New build school delivered by the LEP |
|
|
Knowsley |
Christ the King Catholic and Church of England Centre for Learning |
Jan 09 |
New build school delivered by the LEP |
|
|
Lewisham |
Sedghill |
Jan 09 |
New build school delivered by the LEP |
|
|
Manchester |
Our Lady's RC High School (Higher Blackley Education Village) |
Feb 09 |
New build primary school delivered by the local authority framework |
D&B |
|
Manchester |
North Ridge SEN (Higher Blackley Education Village) |
Feb 09 |
New build primary school delivered by the local authority framework |
D&B |
|
Newcastle |
Jesmond Primary School |
Mar 09 |
||
|
Lambeth |
Elm Court |
Mar 09 |
New build special school delivered by the local authority framework |
D&B |
|
Part new build/remodelling |
|
|
|
|
|
Newcastle |
All Saints College |
Sep 06 |
Modernised as part of a "quick win" BSF project before the LEP was established |
D&B |
|
Sheffield |
Chaucer Business and Enterprise College |
Oct 06 |
Modernised as part of a "quick win" BSF project before the LEP was established |
D&B |
|
Sunderland |
Oxclose Community School |
Jun 07 |
Modernised as part of a "quick win" BSF project |
D&B |
|
Lambeth |
Elmgreen School |
Sep 07 |
Temporary accommodation provided for the school in advance of a complete new build |
D&B |
|
Mancehster |
Newall Green High School |
Sep 08 |
Modernised by the local authority framework |
D&B |
|
Machester |
Gorton Education Village (Cedar Mount High School) |
Sep 08 |
Modernised by the local authority framework |
D&B |
|
Manchester |
St Paul's |
Sep 08 |
Modernised by the local authority framework |
D&B |
|
Waltham Forest |
Kelmscott School |
Sep 08 |
Modernised by the LEP |
D&B |
|
Newcastle |
Benfield School (phase 1 of refurb) |
Sep 08 |
1st phase of a major refurbishment of the school |
D&B |
|
Sheffield |
Yewlands Technology College |
Oct 08 |
Modernised by the LEP |
D&B |
|
Leicester |
Fullhurst Community College |
Jan 09 |
Modernised by the LEP |
D&B |