9  Manchester is confident that it has sufficient capacity to manage the BSF programme - it has a large in-house team and recent experience of managing large scale capital programmes. It is managing BSF from within its Capital Buildings Team.

10  Leadership capacity within the school we visited for a focus group was resourced internally. The Assistant Head was tasked to manage the programme and a Facilities Manager was appointed to oversee the handover and smooth running of the school.

23 

Manchester's model for delivering BSF

Source: Interviews with Manchester City Council managers