Unknown

PFI Project

 

Capital value of change £000

Associated operating cost in first year £000

Description of change

How was the cost validated?

Unknown

 

 

 

 

Haringey - Grouped Secondary Schools

104

3

Fitting out a music technology room. Office and kitchen alterations.

The project team do not know whether the change was competitively tendered, this is a decision left to the SPV. The Authority used technical advisers to advise on cost and negotiate the price, the ultimate decision about whether to accept the cost and proceed was made by the individual school.

Haringey - Grouped Secondary Schools

100

Not available

New temporary teaching huts.

The project team do not know whether the change was competitively tendered, this is a decision left to the SPV. The Authority used technical advisers to advise on cost, the ultimate decision about whether to accept the cost and proceed was made by the individual school.