Environmental regulations and design quality

2.23  Since the deal was signed, there have been numerous changes to the environmental regulations on new buildings. From April 2007 EP is required to meet level 3 of the Government's Code for Sustainable Homes which is 25 per cent above current industry standards. By the end of the development new buildings will have to achieve level 6. Given its role in delivering sustainable homes and communities, EP has persuaded MDL to agree that residential plots will already target a level 4 rating which is likely to increase the costs borne by MDL. In line with its corporate objectives EP is also championing higher quality design for the Peninsula than has been achieved generally across the Thames Gateway.

2.24  The Government has also introduced an overall zero- carbon target for 2016. This target goes beyond what was agreed in outline planning permission and the parties will need to agree how they can work towards the target in line with their commitment to sustainability.